A major lift on Brisbane's Kangaroo Point Bridge
Kangaroo Point Bridge has reached a new construction milestone with the final piece of the 95-metre-tall mast centrepiece installed by Marr Contracting’s M2480D tower crane working on the project.
Located on Brisbane’s busy river, the key challenge for the project was how to construct the bridge mast while minimising potential impacts on the public ferries and private vessels that use the Brisbane River daily.
The BESIX Watpac-led consortium, Connect Brisbane, who is delivering the project on behalf of Brisbane City Council, engaged Marr early in the design phase to develop a lifting strategy that supported their preferred construction methodology and addressed the challenges of constructing the 95-metre-tall mast.
According to BESIX Watpac Project Director, Rowan Riggall, “Our in-house engineering team was instrumental in identifying this crane at tender phase as the preferred lifting solution for the project. After comparing barge crane and tower crane options, the team confirmed the M2480D was the most suitable crane in the Australian market capable of lifting the fully assembled mast head.”
Working with Marr’s Brisbane-based engineers, Robert Bird Group, Marr developed a solution using an M2480D Heavy Lift Luffing (HLL) tower crane with a 64-metre-long boom installed on a platform in the middle of Brisbane River.
This configuration allowed the 25-metre-tall pre-fabricated steel masthead weighing 180 tonnes to be lifted to a height of 95 metres – a feat that wouldn’t have been possible using a more traditional approach of crawler cranes.
The lift was the heaviest to be undertaken as part of Marr’s scope of work including more than 10 major lifts and general construction lifting requirements over a period of 12 months.
“Reaping the benefits of modularised construction with fewer, heavier lifts is not only helping to deliver a safer, more productive site; but also allowing our client to share the economic benefit delivered by the project by engaging more South East Queensland businesses away from the workfront,” said Marr’s Managing Director, Simon Marr.
[edit] ABOUT KANGAROO POINT BRIDGE
An initiative by Brisbane City Council, the Kangaroo Point Bridge will be an iconic landmark destination connecting Brisbane’s CBD and eastern suburbs.
At a length of 460 metres, the bridge will be among the longest span cable stay pedestrian and cycle bridges in the world and a must-visit destination in Brisbane.
In June 2021, Brisbane City Council awarded the contract to design and construct the Bridge to the Connect Brisbane, following a detailed procurement process.
Led by BESIX Watpac, the Connect Brisbane consortium consists of bridge design, engineering and construction specialists including Rizzani de Eccher, WSP, Dissing + Weitling, Blight Rayner, Aspect Studios, Right Angle Studios and Rowland.
Construction of the Kangaroo Point Bridge is anticipated to be completed in 2024.
[edit] Related articles on Designing Buildings
- Amazing cranes.
- Avoiding crane collapses.
- Banksman.
- Bituminous mixing and laying plant.
- Cherry pickers.
- Compressed air plant.
- Concreting plant.
- Construction plant.
- Construction tools.
- Counterweights.
- Cranes.
- Crane supports.
- Crane regulations.
- Driving and riding safely for work.
- Earth-moving plant.
- Electromagnetic overhead cranes.
- Equipment in buildings.
- Excavating plant.
- Forklift truck.
- Gantry.
- Hoists.
- Lifting device.
- Pulley.
- Rubble chute.
- Scaffolding.
- Scissor lift.
- Site storage.
- Stacker.
- Temporary works.
- Types of crane.
- Winch.
- Work at height.
- Work at height regulations.
Featured articles and news
UK Net Zero Carbon Buildings Standard V1 published
Free-to-access technical standard to enable robust proof of a decarbonising built environment.
Prostate Cancer Awareness Month
Why talking about prostate cancer matters in construction.
The Architectural Technology podcast: Where it's AT
Catch up for free, subscribe and share with your network.
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.





















